Investment In Lincoln’s Flood Defences Continues At New Location

United Kingdom – Work to strengthen riverside walls along Lincoln’s Foss Bank is under way, as part of a £6 million investment in the city’s flood defences.

New steel piles are being driven into the riverbank upstream of Brayford Pool, reinforcing the existing defences and maintaining the area’s standard of protection.

Measures are being taken to reduce the potential impact on residents, including a ‘silent piler’ to significantly lessen both noise and vibration.

The work at Foss Bank is being carried out from a pontoon in the river, reducing the need for road closures and footpath diversions. A river traffic light system is in place with staff on hand to make navigation safe for boaters.

Residential boats moored in the area will need to be temporarily moved while the work is underway. And there will be some minor disruption to parking bays on Foss Bank.

The work is expected to be completed in October, subject to water levels.

It is all part of a wider scheme that will maintain the existing standard of flood-risk protection for around 4,000 homes and businesses in Lincoln.

Led by the Environment Agency, the £6 million Lincoln Defences Project began in June 2019.

To date, it has included the refurbishment of Stamp End Sluice and defences at Sincil Dyke next to Lincoln City Football Club, Stamp End, Dixon Street and Spa Road.

Work between Dixon Street and Altham Terrace, where 500 metres of new steel piles were driven into the Witham’s riverbank, was completed last month.

This reinforced the existing defences, reducing the seepage through the bank and maintaining the area’s standard of protection against flooding. The embankment’s footpath has been reinstated, after it was temporarily diverted during the work.

When complete, the entire Lincoln Defences project will have renovated more than 2 kilometres of riverside walls and 3 sluices, as well as introduced environmental improvements. It is expected to generate economic benefits valued at almost £33 million.

Morgan Wray, flood risk manager at the Environment Agency, said:”

Lincoln’s network of defensive walls and sluices work well to reduce the risk of flooding to around 4,000 >properties.

Naturally, despite regular maintenance, they do need to be repaired, improved and updated from time to time.

This investment will ensure they continue to offer the same reliable standard of protection for years to come, >while – at the same time – introducing measures that will enhance the environment for wildlife.

But it’s important to recognise that we can never completely eliminate the risk of flooding, and would urge people to check if they’re at risk, and sign up to receive free flood warnings via GOV.UK/Flood or 0345 988 1188. These will give you invaluable notice when flooding is expected, and details of what you should do to keep safe, as well as protect your home and valuables.”

The Lincoln Defences Project has been funded by the Department for Environment, Food and Rural Affairs as part of its commitments to reduce the risk of flooding to 300,000 properties across the country between 2015 and 2021, and to 336,000 properties between 2021 and 2027.

Work on the Lincoln Defences Project has continued during the coronavirus outbreak, with strict adherence to social distancing measures.