TDPel Media News Agency

Parliament building structure safe from collapse after January blaze

Fact Checked by TDPel News Desk
By Lola Smith

Following the devastating fire that engulfed the South African parliament building, a preliminary report has suggested that the building is safe and not under threat of collapse.

This was revealed on Friday by the Department of Public Works and Infrastructure (DPWI) updating the Joint Standing Committee on the Financial Management of Parliament on the progress of the independent assessment of the fire damage done by the development entity Coega corporation.

A joint statement by presiding officers and the department said: “Current structural damage does not pose a risk of the collapse of the buildings”.

It says there is however severe structural damage to the central structure from the second floor to the sixth.

“Urgent work is required to make parts of the Old Assembly safe to exterior walls and to provide a temporary roof to prevent rain causing damage to lower floors.”

The Coega team completed the bulk of the preliminary assessment to:

  • Assess the fire-damaged buildings in the precinct to pronounce the extent of the damage
  • Provide professional advice on the safety of the structures.
  • Provide measures to temporarily make the structure safe to allow the investigations to proceed unhindered

Coega said that “urgent work is required to make parts of the Old Assembly safe to exterior walls and to provide a temporary roof to prevent rain causing damage to lower floors.”

According to the entity, the damage assessment status is as follows:

  • Loose debris material (roof sheeting, ceiling boards, etc.) on the roof level and 5th floor must immediately be removed which may blow off during windy days and poses a risk.
  • Water in the basement delayed the Final Initial Assessment Phase 1 conclusion
  • HAWKS and fire forensic investigation must first be completed before Phase 2 (final assessment report) can commence
  • Making safe the National Assembly fire-damaged areas to immediately start after the HAWKS and other investigations

It said that phase 2 of the report submission is envisaged by early May 2022 (subject to completion of investigation by Hawks by 1 April 2022)

“The restoration project will commence as soon as all the internal project registration processes have been completed.”

A report by the Sunday Times back in January revealed that the national assembly building was not insured, which leaves the massive costs to rebuild on the shoulders of taxpayers.

Experts estimated that repairs could cost at least R1 billion.

Spread the News. Auto-share on
Facebook Twitter Reddit LinkedIn
10
We are taking you to the next article automatically...You can cancel it below or click Load Now to read it now!
Lola Smith

About Lola Smith

Lola Smith is a highly experienced writer and journalist with over 25 years of experience in the field. Her special interest lies in journalistic writeups, where she can utilize her skills and knowledge to bring important stories to the public eye. Lola’s dedication to her craft is unparalleled, and she writes with passion and precision, ensuring that her articles are informative, engaging, and thought-provoking. She lives in New York, USA.